Odoo Go-Live in 90 Days: Method, Scope, Limits

How an Odoo go-live in 90 days works: a clearly bounded scope, standard before customisation, 60 days of aftercare. And when the longer route is better.

  • AuthorRuetech GmbH
  • Updated
  • Reading time10 min
  • LevelBeginner

Article

ERP projects follow an uncomfortable rule of thumb: they take longer than expected, cost more than planned and deliver less than promised. Industry analysts at WiWo, Group24, and ProAlpha consistently report mid-market projects running 6 to 18 months, with significant cost overruns and adoption issues at go-live.

With Quick Start, Ruetech takes the opposite route: a clearly bounded scope, a fixed price and a go-live after 90 days. It does not suit every project, but it suits many. This guide explains the method, its scope and its limits. The 90 days apply to the scope described here. The binding go-live date for your project is stated in the fixed-price quote.

Quick verdict: A Quick Start go-live in 90 days is realistic with 8 to 25 users, a clearly bounded module scope (accounting, sales, inventory, optionally CRM) and a project team that decides quickly. That requires an honestly sized scope, little customisation and contacts who are available. Without these prerequisites, we recommend a standard implementation of 12 to 20 weeks instead of Quick Start.

Why classic ERP implementations take so long

Average project timelines show a recurring pattern: 9 to 14 months for setups with 25 users. Three causes drive this:

1. Unclear scope at the start

Many projects start with a deliberately broad list of requirements, so that nothing is "forgotten". The result: 200 to 400 requirements, 60 percent of which turn out during implementation not to be essential. They are in the plan anyway.

2. Customisation as a reflex

Instead of checking whether a standard workflow is enough, a customisation is ordered straight away. That extends configuration, testing and training. At every version upgrade the customisations have to be checked again. That is the mortgage on the project.

3. Late stakeholder engagement

Users often see the system for the first time at acceptance testing. Problems that could have been solved two months earlier only surface in training week and push the go-live back.

Together, these three causes turn a 90-day setup into a twelve-month project, even though the original scope could have been delivered in 90 days.

The Quick Start method in five phases

Quick Start works because it removes these three causes. The method in five phases:

Phase 1: Preliminary analysis and specification (weeks 1–2)

We come to your site, talk with management and department heads and map your current processes. The result is a focused specification with:

  • 30 to 60 requirements (instead of 200 to 400)
  • Clear prioritisation: must-have for 90 days, nice-to-have for Phase 2
  • Module selection with standard configuration as the default
  • Roles and permissions concept

What we deliberately do not do in Phase 1: write requirements for hypothetical future cases. We focus on what your users need today to work productively.

Phase 2: Configuration (weeks 3–7)

In a test environment we configure Odoo according to the specification, 80 percent through standard functionality and without custom code. Over these five weeks:

  • Activate and configure modules (accounting, sales, inventory, optionally CRM)
  • Set up master-data structure (chart of accounts, tax rules, item master)
  • Define workflows (sales workflow, goods receipt, invoicing run)
  • Up to 40 hours of customisation for clearly identified special cases (included in the Quick Start package)
  • short training sessions with key users in parallel

Phase 3: Data migration and testing (weeks 8–10)

We export the data from the legacy system, import it into Odoo and reconcile balances, quantities and prices. Acceptance testing by your team takes place in a dedicated test week, not only at go-live.

Phase 4: Go-live (week 11)

Cutover takes place at a quarter- or year-end, with our team on site for the cutover weekend. Users are trained in the days before. The system goes live on Monday morning with our team on standby.

Phase 5: Aftercare (weeks 12–22)

60 days of close support after go-live: daily response readiness, weekly reviews with management, prioritised bug fixes. In this phase we work through whatever comes up in live operation.

After aftercare: handover to a support plan with a fixed monthly fee.

What a 90-day setup typically includes

A Quick Start package usually contains:

  • Modules: accounting with DATEV interface, sales, purchase, inventory. Optionally helpdesk or CRM.
  • Users: 8 to 12, with roles and permissions concept
  • Data migration: master data (customers, suppliers, items, accounts) plus open items, open orders, and inventory at cutover. Historical documents archived as historical data.
  • Interfaces: DATEV export, banking interface, one simple shop connector (e.g. Shopify, Shopware) where relevant
  • Customisation: up to 40 hours of custom development for clearly identified special cases
  • Training: key-user training in Phase 2, user training in Phase 4 (on site)
  • Aftercare: 60 days after go-live

What a 90-day setup usually does not include

The following does not fit into 90 days:

  • Complex multi-company consolidation with three or more subsidiaries
  • Deep industry customisation (e.g. EDI-VDA integration to automotive OEMs, aviation-catering flight-schedule connector)
  • Full in-house manufacturing with MRP in complex production facilities
  • Multi-site logistics with more than three warehouses
  • Migration from heavily customised legacy systems with hundreds of bespoke fields

For these requirements we recommend a standard implementation of 12 to 20 weeks, with a more detailed specification and more room for customisation.

Prerequisites for a successful Quick Start

For the 90-day setup to work, we need three things on your side:

1. A project team that decides quickly

One person with decision authority per main module (accounting, sales, inventory). They must be available during preliminary analysis and configuration, typically 4 to 8 hours per week. If decisions take three weeks, the project takes three times as long.

2. Clean master data

Customer, supplier and item data in reasonably consistent shape. We clean it up with you, but we cannot create data quality out of nothing.

3. Willingness to use the standard

Your business processes follow Odoo's standard functions. If the standard covers 95 percent of your requirements, we do not build costly customisation for the last 5 percent. This is the most important prerequisite.

Quick Start variants

  • Quick Start Standard: for 5 to 10 users and a clear module scope (accounting, sales, inventory).
  • Quick Start Plus: With more substantial data migration, more interfaces, broader training scope.
  • Standard implementation: when Quick Start is too tight, with 12 to 20 weeks and no fixed 90-day frame.

The binding quote, which you receive within five business days of the first call, states the fixed price.

What determines project duration in practice

The actual duration depends less on the industry than on four factors: the scope of the first go-live, the state of the legacy system and master data, the number of interfaces and industry-specific extensions, and the speed of decisions in the project team. Projects with a clear scope, standard processes and clean data stay within the 90-day frame. When a project brings many industry-specific requirements and interfaces, we say so openly and plan a standard implementation of 12 to 20 weeks.

Final take

A go-live in 90 days is not a sales promise but a method for a particular project profile. Companies that accept a clearly bounded scope, stay close to the Odoo standard and provide a project team that decides quickly are working productively in Odoo after 90 days.

Companies with more complexity are better served by a standard implementation of 12 to 20 weeks. We clarify which route suits your project in a free first call.

Book a first call: check whether Quick Start fits (30 minutes)

The steps at a glance

  • 5 steps
  • Time frame22 weeks
  1. Phase 1: Preliminary analysis and specification (weeks 1–2)

    On-site workshop with management and department leads. The output is a focused specification document with 30 to 60 requirements, clear must-have vs nice-to-have prioritisation, module selection with standard configuration as the default, and a roles and permissions concept.

  2. Phase 2: Configuration (weeks 3–7)

    Configuration in a test environment, 80 percent through standard functionality and without custom code. Activate modules (accounting, sales, inventory, optional CRM), set up master-data structure, define workflows, and apply up to 40 hours of targeted customisation for special cases. Key-user training in parallel.

  3. Phase 3: Data migration and testing (weeks 8–10)

    Extract data from the legacy system, import into Odoo, and validate balances, quantities, and prices. Acceptance testing by the customer team in a dedicated test week, not only at go-live.

  4. Phase 4: Go-live (week 11)

    Cutover migration at quarter- or year-end. Cutover weekend with the Ruetech team on site. End-user training in the days before. Live launch on Monday morning with a standby team.

  5. Phase 5: Aftercare (weeks 12–22)

    60 days of close support after go-live with daily response readiness, weekly reviews with management and prioritised bug fixes. Then handover to a support plan with a fixed monthly fee.

Frequently asked questions

What if the project costs more than the fixed price?

We cover additional effort within the agreed fixed-price scope. If requirements appear during execution that weren't in the original specifications, we discuss openly whether to pull them into the Quick Start or move them to Phase 2. You decide.

What if we miss the 90-day target?

It is rare, but it can happen. The most common causes: master data arrives later than planned, someone in the project team is unavailable, or external factors such as supplier interfaces or the tax adviser's sign-off are delayed. As soon as we see a delay, we tell you and adjust the plan.

Can we expand later?

That is exactly what we recommend. Quick Start lays the foundation. In Phase 2, 3 to 6 months after go-live, we add modules such as CRM, marketing, helpdesk or an online shop, or deepen industry-specific customisation.

What if our legacy system is heavily customised?

Then Quick Start is often not the right route. In a one-day preliminary analysis we check what your migration can realistically achieve in 90 days, and tell you if a standard implementation of 12 to 20 weeks makes more sense.

About this article

Author
Ruetech GmbH
Published
Updated
Reading time
10 min

Migration check

Replacing an existing system?

Four questions about your plans are enough. Within one business day you receive a one-page written assessment: the requirements and risks of your migration. You can pass the page on to management, finance and IT.

Written assessment within one business day · Odoo Silver Partner

Migration check

Your migration check: four questions about your planned system change.

Within one business day, we will summarise the requirements and risks of your migration on one page.

Your starting point
Where should we reply?

Only used to handle your enquiry. Details in our privacy policy.

Pick a slot